Week 19

It is starting to look like a real building.

Earlier in the week the Shear Walls were installed on the East and West End of the building. Lots of blocking fire/smoke stops and finishing around doors and windows.

They also started the bottom grey section around the building.

The south roof of the lower building was also started along with the wall sheeting. Next week NIPSCO is scheduled to pull in the temporary power to the building.  This is planned for Tuesday.

Bloomfield will also mobilize on site to start the underground plumbing.  ECE will be assisting Bloomfield with a mini excavator inside the building to dig the trenches.

Press Releases

United Way NWI Partners with MAAC Foundation to Expand Emergency Medical Responder Training OpportunitiesMAAC Foundation Celebrates 19 Winter 2026 EMT Academy Graduates

MAAC Foundation Celebrates 19 Winter 2026 EMT Academy Graduates

MAAC Foundation Receives READI Funds for Public Safety Innovation Campus

MAAC Foundation donates $50K to K9 agencies

Engineering a Legacy: PNW alumnus Stewart McMillan

MAAC News & Updates

Scroll To Top