Week 15
March 25, 2026
With the warmer weather and melting snow, the area turned into a bit of a wet sand pit that slowed the ability of installing the trusses on the one-story portion of the building. Crews continued to work but switched to work that they could safely get to. Window frames were started along with additional cross bracing. The end wall between the 1 and 2 story was installed on Thursday to help strength the movement of the building during the high winds that we saw today. Additional cabling was also put in place.

Posted in Construction Updates