Week 18

Cleary has started to install the roof sheeting on the 2 story section. Cleary also continued to install the interior wall supports in the one-story section.  They are hoping to…

b7cd4e72-569d-4b84-ac7f-4eb29296a121

Week 17

Cleary worked on various smoke blocking along with the soffits.  They did start putting sheeting on the roof.   Cleary plans on working Friday depending on the weather.

19c535fb-d80e-40d5-b649-5403e22366a8

Week 16

The week seen more activity than the last couple of weeks. Circle R was back to work on additional light pole bases. ECE worked with H&G Underground Utilities to connect…

05d35874-7a83-4409-ae67-0ccc5169abf2

Week 15

With the warmer weather and melting snow, the area turned into a bit of a wet sand pit that slowed the ability of installing the trusses on the one-story portion…

b440c48d-cac8-44bc-803d-56bac6ea4262

Week 14

Circle R worked on setting forms for the light poles and poured concrete on Thursday along with the transformer pad.  The Transformer Pad also has the temporary power stand set…

Press Releases

MAAC Foundation Receives a Dollar-for-Dollar Matching $50,000 Grant from Legacy Foundation

United Way NWI Partners with MAAC Foundation to Expand Emergency Medical Responder Training OpportunitiesMAAC Foundation Celebrates 19 Winter 2026 EMT Academy Graduates

MAAC Foundation Celebrates 19 Winter 2026 EMT Academy Graduates

MAAC Foundation Receives READI Funds for Public Safety Innovation Campus

MAAC Foundation donates $50K to K9 agencies

Scroll To Top