Week 10

The week started out well on Monday with Cleary crews arriving on site and moving materials around to get organized and start setting column brackets on the foundation wall.  On Tuesday Cleary finished installing the column brackets and started setting posts on the East side of the building.  Crews did not work on Wednesday or Thursday due to the weather, but additional materials were delivered by Cleary.