Skip to content
image (6)

Week 10

The week started out well on Monday with Cleary crews arriving on site and moving materials around to get organized and start setting column brackets on the foundation wall.  On Tuesday Cleary finished installing the column brackets and started setting posts on the East side of the building.  Crews did not work on Wednesday or Thursday due to the weather, but additional materials were delivered by Cleary.

Press Releases

MAAC Foundation Invites Public to First-Ever MAACtoberfest Event

MAAC Foundation Receives a Dollar-for-Dollar Matching $50,000 Grant from Legacy Foundation

United Way NWI Partners with MAAC Foundation to Expand Emergency Medical Responder Training OpportunitiesMAAC Foundation Celebrates 19 Winter 2026 EMT Academy Graduates

MAAC Foundation Celebrates 19 Winter 2026 EMT Academy Graduates

MAAC Foundation Receives READI Funds for Public Safety Innovation Campus

MAAC News & Updates

Scroll To Top